# WBV2-P26-004 status
- task: `WBV2-P26-004`; parent: `WBV2-P26-003`; status: `done`
- capability family: `RENDER.COMPOSITOR_SEQUENCER`; source-backed commands wired: `1`
- implementation: render/compositor/sequencer capability gates are wired; renderer production verification remains deferred
- verification wave: `DEFERRED`; no Chromium receipt or completion overlay written
- inventory unchanged: `6900` total, `281` legacy completed, `6618` legacy pending, `290/6609` effective carried forward
- nextTask: `WBV2-P26-005`